I. Introduction
In the material procurement chain of overseas EPC engineering projects such as oil and gas, petrochemical, LNG, new energy, and offshore engineering, pipe fitting prototyping is a key bridge connecting technical solutions and mass production.Unlike samples of ordinary civilian products, pressure pipe fittings are pressure-bearing special equipment components. Foreign trade prototyping is not merely about making a physical object for customers to view its appearance, but a comprehensive verification of the entire process covering design drawings, raw materials, thermoforming, heat treatment, bevel processing, surface treatment, and marking schemes.The root cause of mass quality accidents in many foreign trade projects lies in the absence of rules during the prototyping stage: specially crafted premium samples are used instead of production-process samples, drawing understanding deviations occur, raw material heat numbers do not match, and forming thinning exceeds limits. By the time mass production is completed and third-party TPI supervision intervenes for inspection, it is discovered that the products cannot meet the project technical specifications, resulting in huge raw material losses, production rework, shipping delays, overseas port detention, and project delay compensation losses.
Foreign trade pipe fitting prototyping work runs through the entire process of technical liaison, raw material procurement, forming and processing, inspection and testing, documentation preparation, logistics delivery, and sealed sample retention.Different types of samples have clear distinctions in applicable scenarios, manufacturing rules, inspection items, and documentation delivery requirements.Inquiry samples are only used for commercial display;Development samples are used for process feasibility verification of non-standard, special material, and special working condition pipe fittings;The pre-production sample must fully replicate mass production conditions and serve as the benchmark for subsequent batch production.At the sampling stage, costs are low, and there is ample room for rectifying defects found;once mass production begins, the cost of rectifying any process defect will rise exponentially.
This article discusses core rules including the basic classification of sampling for foreign trade pipeline fittings, pre-technical review rules, raw material selection rules, forming processing and heat treatment control, sample inspection items, documentation requirements, sample packaging and shipping, and sample change management. It sorts out common misconceptions at the sampling stage and establishes a standardized sampling control process and risk prevention countermeasures, providing a theoretical basis and practical guidance for domestic pipeline fitting manufacturers carrying out sampling work for foreign trade EPC projects.
II. Classification and Basic Rules of Sampling for Foreign Trade Pipeline Fittings
2.1 Inquiry Sample (Commercial Display Sample)
Inquiry samples are mostly used for early-stage business communication of a project. Customers only need to visually inspect the appearance, surface treatment method, and marking style of the fitting, and generally do not conduct full performance testing.Inquiry samples can be made from standard fittings in stock; it is not mandatory to use raw materials from the heat number specified by the project, and some non-destructive testing items can be simplified.Inquiry samples serve only as an appearance reference and must strictly not be used as the acceptance benchmark for mass production. During the business engagement stage, the customer must be informed in writing by email of the sample's attributes, to prevent the customer from mistakenly believing that the inquiry sample is the mass production benchmark, which could cause subsequent acceptance disputes.The sampling rules for inquiry samples are relatively lenient, but the physical appearance and marking style should match the customer's requirements as closely as possible to reduce customer perception deviations.
2.2 Development Sample (Trial Production Sample)
Development samples are suitable for non-standard custom pipe fittings, high-pressure thickened pipe fittings, low-temperature alloy pipe fittings, eccentric reducers, branch outlets, and other unconventional products.When customer drawings involve special dimensions, special materials, or special forming processes and there are no mature mass production process parameters, development samples need to be made to verify forming feasibility.Development samples may use trial molds and do not necessarily use mass production tooling. The core verification objectives include forming springback, wall thickness thinning at the outer arc of elbows, ovality, groove forming effect, and material mechanical properties after heat treatment.Development samples must undergo full-dimensional measurement and visual appearance inspection. Samples of high-pressure and alloy materials require additional PMI spectral analysis and UT ultrasonic wall thickness testing, and when necessary, PT penetrant non-destructive testing to detect forming cracks.If development samples exhibit defects such as out-of-tolerance dimensions, excessive wall thickness thinning, or surface cracks, the deviations need to be recorded, and the molds, forming temperature, and heat treatment process adjusted for re-trial production until the drawing and standard requirements are met.Only after the development sample passes can the pre-production sample stage be entered.
2.3 Pre-production Sample (Production Benchmark Sample)
The pre-production sample is the most important sample type in the foreign trade sampling system. Core rule: raw materials, heat/batch numbers, forming molds, heat treatment processes, sandblasting and coating, and steel stamp marking schemes must all be fully consistent with the subsequent mass production; specially machined samples are not allowed.Many enterprises, in order to quickly pass customer review, separately machine samples with perfect appearance while using ordinary forming processes for mass production, resulting in inconsistency between the sample and mass production quality. This is the most serious sampling risk in foreign trade pipe fitting projects; once overseas owners and TPI supervisors verify and discover this, they have the right to directly reject the entire batch of goods.The pre-production sample represents the true quality level of mass production and requires the execution of a complete ITP inspection and test plan, with the full set of inspection items, original records, and material documentation delivered to the customer for review.After the pre-production sample review is passed, it can serve as the sealed reference sample for subsequent factory inspection of mass production and overseas unpacking comparison.
2.4 General Priority Rules for Sampling
All technical requirements for foreign trade pipe fitting sampling follow the priority: project technical agreement > ITP inspection and test plan > product manufacturing standards (ASME B16.9, ASME B16.5, EN10253) > ASTM material standards.If the project technical specifications impose requirements stricter than the basic international standards, the sampling manufacturing and inspection determination must be based on the project technical agreement, and the minimum limits of the standards must not be directly applied.Before sampling, the drawing version must be locked. If any modification is made to the drawing, the original sample becomes invalid and re-sampling is required.
III. Pre-sampling Technical Review Rules (Before Sampling Starts)
Before material cutting and sample processing, the sales, technical, and quality inspection departments must jointly complete the review of drawings and technical documents. Sampling must not start before the review is completed.Many sampling failures stem from misunderstandings of drawings. Directly arranging processing based only on a salesperson's relay of the customer's verbal requirements causes the entire sample to be scrapped.
First, collect the complete set of technical documents, including versioned engineering drawings, MTO material lists, project technical specifications, ITP inspection plans, applicable standards, material grades, pressure class Class, SCH wall thickness, dimensional tolerances, steel stamp marking content, non-destructive testing requirements, surface treatment requirements, and additional requirements for special service conditions, such as NACE sour service resistance, low-temperature impact, and PED EU pressure equipment certification.
Second, carry out the technical check of drawings, verify the fitting diameter, wall thickness, center-to-face dimensions, bevel type, and sealing face type, and identify contradictions in drawing parameters, risks of mixed use across standards, and ambiguities in non-standard dimensions.If the drawings contain ambiguous, missing, or conflicting content, a written technical clarification must be initiated to the customer, written confirmation must be obtained from the customer, the drawing version number must be locked, and email records must be retained before sampling can start.Oral clarifications are invalid and cannot serve as a basis for sampling.
Third, planning the sampling scheme, specifying the sample quantity, delivery cycle, inspection items, document list, party responsible for the samples, mold costs, and responsibility for sample express delivery.For non-standard pipe fittings, it is necessary to evaluate the mold manufacturing cost, forming difficulty, and forming thinning risk, predict process feasibility, assess sampling costs, stipulate in the commercial contract whether the sample fee can be deducted from subsequent bulk orders, and clarify the remaking responsibility when samples fail inspection.
Fourth, sampling risk assessment: for difficult-to-machine materials such as large-diameter thin-wall pipe fittings, low-temperature alloys, and high-nickel alloys, assess risks such as forming springback, heat treatment deformation, and iron ion contamination, and formulate response plans in advance.
IV. Rules for Selecting Raw Materials for Sampling
Raw material control is a core rule for sampling in foreign trade pipe fittings. Material issues are unacceptable major defects; once the material grade does not match, the sample is directly voided.
1. Raw material grades must strictly match the customer's technical requirements; materials such as A234 WPB, A403 WP304, and A105 must not be replaced arbitrarily.The raw materials for pre-production samples must be locked to a fixed heat number, re-inspection must be completed upon raw material arrival at the factory, PMI spectral testing must be carried out, chemical composition must be verified, mechanical property re-testing must be added for alloy materials, and the raw material MTC material certificates must be retained.If the development sample is only for process validation, a similar heat number of the same material may be used, but the formal pre-production sample must use raw materials from the same batch as the subsequent mass production.
2. Raw materials shall be stored in partitioned management, with carbon steel, stainless steel, and alloy steel stored separately. Stainless steel raw materials must not come into direct contact with carbon steel to prevent iron ion contamination.The surface of raw materials shall be free from defects such as cracks, lamination, scabs, rust, and inclusions. Visual inspection shall be carried out before cutting, and MT/PT testing shall be performed when necessary.
3. During the raw material cutting process, mark transfer shall be properly carried out. The raw material heat number shall follow the blank throughout the process, maintaining traceability at all times to avoid material mixing.For sample blank cutting dimensions, machining allowance shall be reserved for forming. Key considerations include wall thickness reduction during elbow forming and springback during hot push forming, to ensure that the wall thickness at any position after forming is not less than the standard minimum wall thickness limit. ASME B16.9 specifies that the wall thickness at any position of pipe fittings shall not be less than 87.5% of the nominal wall thickness. When the project has higher requirements, the project specifications shall be followed.
V. Precautions for Forming, Heat Treatment, and Surface Processing During Sampling
5.1 Forming Process Control
For the forming process parameters of hot push, cold bending, pressed tees, and reducers, the pre-production sample must be consistent with mass production. The forming temperature, pushing speed, and mold dimensions shall not be adjusted arbitrarily.During the forming process, focus on monitoring the wall thickness reduction in the outer arc area of the elbow; after forming large-diameter fittings, check the ovality and control the out-of-roundness of the end faces.After forming, inspect the fitting body; cracks, laps, scabs, tears, and other harmful defects are not allowed.If slight orange peel occurs during forming, the local wall thickness must be evaluated; if the wall thickness meets the standard, it may be retained;Severe orange peel accompanied by local thinning that exceeds the limit means the sample is judged unqualified.
Bevel machining shall be performed in accordance with ASME B16.25; the bevel angle and root face dimensions shall be machined strictly according to the drawing, and the bevel end face shall be free of chipping, burrs, and rolled edges.The bevel is the core area for on-site welding; during the sampling stage, the bevel forming quality must be verified to prevent bevel machining defects from being carried into mass production.
5.2 Heat Treatment Rules
For fittings that require heat treatment (carbon steel, low-alloy, and low-temperature fittings), the sampling heat treatment process (heating temperature, holding time, cooling method) must be consistent with that of mass production.After heat treatment is completed, verify the hardness indicators; low-temperature pipe fittings also require impact testing.Improper heat treatment can cause material mechanical properties to fall below standards and lead to stress cracks. During the prototyping stage of alloy pipe fittings, heat treatment curve records must be retained as part of the sample documentation.Heat treatment and solution treatment of stainless steel pipe fittings shall be strictly carried out in accordance with ASTM material specifications to prevent the risk of intergranular corrosion.
5.3 Marking, Sandblasting, and Coating
Steel stamp marking strictly follows the MSS SP-25 specification. The marking content includes the manufacturer's trademark, material grade, NPS size, SCH wall thickness, heat number, and governing standard.Carbon steel pipe fittings may use steel stamp pressing, with the pressing depth controlled to avoid local wall thickness reduction;Stainless steel and high-alloy pipe fittings are prohibited from hard steel stamp pressing; electrochemical etching marking is used instead to prevent stamping stress from inducing cracks.Markings must be clear. When applying primer, avoid the marked areas to prevent covering the steel stamps.
For sandblasting and rust removal, carbon steel pipe fittings commonly use Sa2.5 grade, with quartz sand or steel grit selected as the abrasive;Carbon steel abrasives are prohibited for sandblasting stainless steel pipe fittings; glass beads or stainless steel grit shall be used to prevent iron contamination.Primer spraying requires a continuous and uniform coating, with no sagging, pinholes, or missed spraying; painting is prohibited in weld groove areas to avoid porosity defects during welding.
VI. Inspection and Testing Rules for Prototype Samples
After sample processing is completed, tiered inspection must be completed: workshop self-inspection, quality department re-inspection, and third-party testing added as required by the project.Inspection items must be documented in original measured records; it is not acceptable to only fill in a pass conclusion.
1. Visual appearance inspection: inspect the inner and outer surfaces of pipe fittings for cracks, laps, arc burns, pits, and scratches, and check the groove end faces for impact damage.Distinguish between hazardous defects and defects that can be repaired by grinding; cracks, delamination, and double-skin shall be directly judged as scrapped samples, and it is not allowed to submit them to the customer after grinding repair.After grinding shallow scratches and minor dents, the remaining wall thickness must be rechecked with UT thickness measurement to ensure it meets the minimum wall thickness limit, and the ground area shall be smoothly transitioned.
2. Full dimensional tolerance inspection: use a Pi tape to measure the outer diameter of the large-diameter end, and use an ultrasonic thickness gauge to measure wall thickness at multiple points, focusing on the thinnest position of the outer arc of the elbow;Measure the center-to-end dimension, overall length, bevel angle, root face, ovality, and end face perpendicularity, and judge according to ASME B16.9 or EN10253 tolerances.
3. Material PMI spectral testing: carbon steel, stainless steel, and alloy pipe fitting samples must undergo PMI to confirm the material grade and prevent material mix-ups.
4. Non-destructive testing NDT: according to the project ITP requirements, carry out MT magnetic particle and PT penetrant testing to check for surface cracks;For high-pressure and sour service projects, UT ultrasonic internal defect testing can be added.
5. Additional performance tests: low-temperature pipe fittings shall be subjected to impact tests, and high-pressure pipe fittings may undergo hydrostatic tests as required by the owner; all test records shall be archived and kept.
After sample inspection is completed, issue a complete sample inspection report, record all measured data, take physical photos from multiple angles, and retain video records of the inspection process.Minor deviations in samples must not be concealed; a deviation statement must be issued, specifying the deviation location and values, assessing the impact on usage safety, and submitted to the customer for written waiver. Samples must not be shipped without the customer's written approval.
VII. Rules for Preparing Sample Supporting Documentation
For sampling of foreign trade pipe fittings, physical samples and technical documentation are equally important. In technical reviews by overseas EPC customers, missing documentation will directly result in the sample review being deemed invalid.The sampling documentation package includes: drawings with version numbers, sample inspection reports, dimensional measurement record sheets, appearance inspection records, raw material MTC material certificates, heat number traceability information, PMI spectral reports, NDT non-destructive testing reports, heat treatment curve records, steel stamp marking photos, and sample deviation statements (if any).The heat number, material, and specifications in the documentation must correspond one-to-one with the physical items, and the documentation version must remain consistent with the drawing version.According to customer requirements, provide electronic PDF files, and send paper documentation together with the sample package.The documentation must be standardized and comply with the internationally accepted format of EN10204 3.1 certificates.
VIII. Precautions for Sample Packaging and Logistics Shipping
Sample packaging must be suitable for international long-distance express delivery, preventing the bevels and fitting surfaces from being bumped and damaged during transportation.Bevel assemblies are matched with plastic protective caps, and stainless steel fittings are individually wrapped in protective film and kept separate from carbon steel parts to avoid iron ion contamination.Rubber soft pads are added between fittings to prevent mutual impact that could cause dents and scratches.The outer packaging uses sturdy wooden crates or thickened cardboard boxes, with the project number, sample number, fitting specifications, and material marked on the box, and a packing list placed inside.
Before shipping, verify the express waybill, simultaneously send the tracking number, packing list, and full set of electronic documents to the customer, track the logistics throughout the process, and anticipate customs clearance risks.When the samples arrive at the customer's warehouse, remind the customer to open the boxes and inspect them; if there is any damage from bumps during transportation, immediately take photos as evidence and assess whether re-sampling or supplementary samples are needed.
IX. Rules for Sample Review, Changes, and Sealed Sample Management
After receiving the samples, the customer conducts retesting and review, and the feedback conclusion is generally divided into approved, conditionally approved, and not approved.After receiving customer review comments, the sales, technical, and quality inspection teams analyze the issues one by one, form a rectification checklist, and attach defect photos, root cause analysis, and corrective and preventive measures.If the sample is judged unqualified, evaluate the modification plan, adjust the process, molds, and raw materials, and re-produce samples.All communications and rectification plans must be archived in writing via email; verbal communication is invalid.
After the pre-production sample is approved in writing by the customer, execute the sealed sample process. Affix a label to the physical sealed sample indicating the project name, order number, pipe fitting specification, material, heat number, applicable standard, and sealing date, and both buyer and seller shall sign and seal it.Sealed samples are generally in triplicate, with one copy each retained by the supplier, the customer, and the third-party supervision agency, serving as the benchmark for subsequent mass production inspection.After the sample is sealed, no technical changes—including changes to material, forming process, marking, dimensions, or surface treatment—may be implemented without authorization. A change application must be submitted with test data and impact assessment, and written approval from the customer must be obtained;For major change items, samples must be re-produced, re-reviewed, and re-sealed; old sealed samples shall be marked as void and must no longer be used as acceptance criteria.Retained samples shall be stored in a moisture-proof and dust-proof environment; stainless steel samples shall be stored separately and inspected regularly to prevent rust, bumps, and damage.
Ten. High-frequency misunderstandings in sampling for foreign trade pipeline fittings
Misunderstanding 1: Using precision-machined special parts as samples, inconsistent with mass production processes
In order to pass customer inspection in one go, precision-machined perfect samples are specially selected, while ordinary forming processes are used for mass production, causing the quality of bulk goods to be lower than that of the samples.Pre-production samples must use mass production molds, raw materials, and heat treatment processes to truly reflect the quality of bulk goods; premium samples will bring huge performance risks.
Misunderstanding 2: Arranging sampling based only on the customer's verbal description, lacking technical clarification of drawings
Without locking the drawing version, without written clarification of drawing ambiguities, directly cutting materials for processing, only to discover upon sample completion that the drawings were misunderstood, resulting in the entire sample being scrapped and delaying the project cycle.
Misunderstanding 3: Directly using development samples as pre-production samples and sealing sample benchmarks
Development samples use trial molds and do not represent mass production processes; they cannot be directly upgraded to pre-production samples and sealing sample benchmarks. Many sales staff confuse sample levels, causing dimensional deviations in subsequent mass production.
Mistake 4: Focusing only on appearance during sampling while ignoring wall thickness reduction, heat treatment, and non-destructive testing
Only checking the external dimensions, not measuring the minimum wall thickness of the elbow's outer arc, and not performing heat treatment or NDT inspection. The sample looks acceptable in appearance, but its pressure-bearing performance does not meet the standard, and it is rejected during the customer's technical review stage.
Mistake 5: Concealing minor deviations in samples and waiting for the customer to discover them on their own
If dimensional or appearance deviations in samples are not disclosed in writing in advance, and the customer discovers them upon re-inspection, they will question the supplier's integrity in quality control, directly reject the sample, and may even cancel project cooperation.If deviations exist, a deviation application must be submitted in advance to obtain the customer's written waiver.
Mistake 6: Simplifying sampling documentation by sending only the physical item, without the full set of MTC and NDT reports
In technical reviews for overseas EPC projects, documentation is a mandatory requirement. Without material and non-destructive testing documents, samples cannot complete technical approval, delaying project progress.
Mistake 7: Continuing to use old-version retained samples after drawing changes
The drawing parameters were modified, but no new sampling was done. The old sample continued to serve as the sealed reference sample, and mass production was carried out according to the new version of the drawing. The actual product was inconsistent with the sealed sample, resulting in a major dispute during the acceptance stage.
Misconception 8: Simplified sample packaging, lacking bevel protection, resulting in damage from knocks during transportation.
The sample passed the factory inspection, but lacked protective caps, and the packaging had no soft padding. During international express delivery, the bevel was damaged by knocks. The customer directly judged the sample as unqualified during unpacking inspection, requiring re-sampling and increasing time and cost.
XI. Risk Identification and Loss Analysis in the Sampling Process
The risks brought by ineffective sampling control run through the entire process of business communication, sample manufacturing, customer review, and mass production.Omissions in drawing review in the early stage of sampling, misunderstandings of drawings, and repeated remaking of samples lengthen the project cycle and increase mold, raw material, and testing costs;Mixed raw materials and incorrect material grades cause the sample to be directly rejected by the customer, resulting in the loss of the project order.
If pre-production sample verification is not carried out and mass production is directly launched, the mass-produced products' forming process, dimensional tolerances, and markings do not conform to the customer's technical specifications, and the entire batch of goods is rejected, causing losses in raw material processing costs, international ocean freight, port demurrage charges, and returns.During the pipeline prefabrication stage, poor fitting and matching of pipe fittings led to extensive on-site grinding and rework, delaying the EPC project schedule and triggering the late-delivery compensation clause in the procurement contract.When quality disputes arise during the warranty period, the lack of sampling records and sealed sample documentation makes it difficult to provide evidence in commercial negotiations, significantly increasing the risk of customer claims.
Sampling is a front-end risk checkpoint: identifying defects in process, drawings, and materials at the sample stage costs far less to rectify than rectifying them after mass production begins. The essence of implementing sampling rules is to move quality risks upstream and avoid substantial losses.
XII. Optimization Measures for the Sampling System of Foreign Trade Pipe Fittings
1. Establish a sample tiered management system, distinguishing inquiry samples, development samples, and pre-production samples; clearly define the manufacturing standards, raw material requirements, inspection items, and document checklists for each type of sample; prohibit mixing sample benchmarks across tiers; establish a sampling ledger with unified numbering, and record sample status, drawing versions, and review results.
2. Implement a pre-sampling drawing review and technical clarification mechanism. Before sampling begins, technical personnel shall complete a full-item verification of the drawings. If the drawings contain ambiguities or conflicting parameters, written clarification must be obtained, the drawing version must be locked, and any drawing change shall automatically trigger the sample update process.
3. Standardize sampling inspection checklists. Distinguish carbon steel, stainless steel, alloy steel, and high-pressure low-temperature pipe fittings, develop sampling inspection checklists, inspect dimensions, appearance, PMI, UT, and NDT item by item, retain measured data and photos, and ensure inspection records are fully traceable.
4. Implement full-process traceability control of raw materials. Re-inspect raw materials upon warehousing for sampling, properly transfer heat number markings, store them in separate zones, and isolate stainless steel from carbon steel. For pre-production samples, lock the raw material heat numbers to keep them consistent with the raw materials for mass production, and eliminate material mixing.
5. Curing, forming, and heat treatment processes: the forming temperature, molds, and heat treatment parameters of pre-production samples shall all be recorded and archived; mass production shall use the same processes, and process parameters must not be adjusted arbitrarily.
6. Standardize the sample review, change, and sealed sample processes; sealing of samples may proceed only after written customer approval;after a sample is sealed, any technical change must be submitted as a formal change request and implemented only after written customer approval; major changes require new sampling and sealing.
7. Cross-departmental collaboration among sales, technical, and quality inspection teams: sampling projects must not be handled solely by sales staff; the technical team is responsible for checking drawings and standards, the quality inspection team is responsible for sample testing records, and the three parties jointly review customer feedback and formulate corrective plans.
8. Standardize sample packaging and logistics: bevel protection caps and soft isolation pads are standard equipment; recheck the appearance before shipping samples to confirm there is no damage from handling during transport; deliver the full set of electronic documents to the customer in advance to reduce the risk of nonconformity upon unpacking.
XIII. Conclusion
Sampling for foreign trade pipeline fittings is not simply machining a physical item for the customer to inspect; it is a standardized technical verification system that includes drawing review, raw material control, forming and heat treatment, full-item inspection, documentation support, logistics delivery, and sealed sample changes.Samples are divided into inquiry samples, development samples, and pre-production samples; different samples are subject to different manufacturing rules, and pre-production samples must replicate all mass production conditions, with specially made premium samples strictly prohibited.
Sampling work must strictly follow international standards such as ASME and EN as well as project technical agreements, with key control over drawing versions, raw material heat numbers, forming thinning allowance, dimensional tolerances, steel stamp markings, and non-destructive testing, accompanied by complete and traceable technical documentation.Enterprises need to avoid typical pitfalls such as inconsistency between samples and mass production, misunderstanding of drawings, concealment of sample deviations, and insufficient packaging protection, and establish a cross-departmental collaborative sampling control mechanism.Identify drawing, material, and process defects in advance during the sampling stage, complete verification at a lower cost, reduce from the source the risks of rejection, rework, and claims after mass production, and enhance the contract performance capability and market reputation of domestically produced pressure-bearing pipeline fittings in overseas EPC engineering projects.
References
[1] ASME B16.9, Factory-Made Wrought Buttwelding Fittings [S]. American Society of Mechanical Engineers.
[2] ASME B16.5, Pipe Flanges and Flanged Fittings [S]. American Society of Mechanical Engineers.
[3] ASME B16.25, Buttwelding Ends [S]. American Society of Mechanical Engineers.
[4] EN10253, Buttwelding Fittings [S]. European Committee for Standardization.
[5] MSS SP-25, Standard Marking System for Valves, Fittings, Flanges, and Unions [S]. Manufacturers Standardization Society.
[6] ASTM A234/A234M, Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service [S]. American Society for Testing and Materials.
[7] ASTM A403/A403M, Standard Specification for Wrought Austenitic Stainless Steel Piping Fittings [S]. American Society for Testing and Materials.
[8] TSG 31-2025, Safety Technical Regulation for Industrial Piping [S]. Special Equipment Bureau of the State Administration for Market Regulation.
[9] NB/T47013, Nondestructive Testing of Pressure Equipment [S]. Energy Industry Standard.
[10] PED 2014/68/EU, Pressure Equipment Directive of the European Union [S]. European Commission.
[11] GB/T12459, Steel Butt-Welding Seamless Pipe Fittings [S]. National Technical Committee for Standardization of Pressure Piping.
[12] GB/T 8923, Rust Grades and Preparation Grades of Steel Surfaces Before Application of Paints or Related Products [S]. State Administration for Market Regulation.
[13] Li Xuedao. Practical Guide to Foreign Trade Procurement and Quality Control of Pressure Piping Components [M]. Beijing: China Machine Press, 2023.
[14] Zhang Lei. Material Procurement Management for International EPC Projects [M]. Beijing: China Architecture & Building Press, 2022.
[15] Wang Jian. Research on Risk Control of Pipeline Material Procurement in International EPC Projects in the Oil and Gas Industry [J]. Petroleum Engineering Construction, 2024.